roadmap

majiayu000's avatarfrom majiayu000

View and update the development roadmap. Use at the start of each session to understand current progress and next priorities.

⭐0stars🔀0forks📁View on GitHub🕐Updated Jan 5, 2026

When & Why to Use This Skill

The Roadmap skill is a high-precision planning agent designed to manage the software development lifecycle through a rigorous 'Planner Protocol.' It facilitates the creation of structured development roadmaps by breaking down complex specifications into traceable tasks, calculating realistic timelines with built-in buffers, and identifying critical path dependencies. By ensuring every task links directly to technical specs and test suites, it provides a single source of truth for project progress and priority alignment.

Use Cases

  • Session Synchronization: Use at the start of every development session to instantly retrieve the current status of the roadmap and determine the next high-priority tasks.
  • Rigorous Task Estimation: Generate detailed task breakdowns that include optimistic and pessimistic estimates, applying a 2.5x multiplier and 20% weekly buffer to prevent project delays.
  • Requirement Traceability: Map implementation tasks directly to SPEC_IDs, INV_IDs, and TEST_IDs to ensure 100% coverage and compliance with architectural requirements.
  • Risk & Dependency Analysis: Automatically generate dependency graphs and risk assessment tables to identify potential bottlenecks, such as external API volatility or logic complexity.
  • Automated Progress Tracking: Maintain a version-controlled ROADMAP.md that tracks week-over-week goals, exit criteria, and task completion status for stakeholders.
nameroadmap
descriptionView and update the development roadmap. Use at the start of each session to understand current progress and next priorities.

GATE 4: PLANNING — PLANNER PROTOCOL

Agent: PLANNER Gate: 4 of 6 Prerequisite: Gate 3 (Test Design) COMPLETE Output: docs/planning/ROADMAP.md with traced tasks


GATE 4 ENTRY CHECKLIST

Before proceeding, verify:

  • .fortress/gates/GATE_3_TEST_DESIGN.md exists
  • All test stubs exist in tests/
  • TEST_MATRIX.md is complete
  • pytest --collect-only succeeds

If any checkbox fails: STOP. Complete Gate 3 first.


PLANNER PROTOCOL

Core Principle: TASKS TRACE TO SPECS

❌ FORBIDDEN: "Implement feature X"
✅ REQUIRED: "Implement S001 - Package validation"
             TRACES: S001, INV001, INV002
             TESTS: T001.1-T001.10

Every task MUST link to:

  1. SPEC_ID(s) it implements
  2. INV_ID(s) it enforces
  3. TEST_ID(s) it must pass

Step 1: Define Task Size Limits

Rule Limit Reason
Max task size 8 hours Smaller = better estimates
Estimation multiplier 2.5x Always over-estimate
Buffer per week 20% Unexpected issues

Step 2: Create Task Breakdown

For each SPEC_ID, create implementation tasks:

## TASK: W1.1 — Implement Core Types

### Traces
- SPEC: S001, S002
- INVARIANTS: INV001, INV002
- TESTS: T001.1-T001.5

### Definition
Implement the core data types for PackageRisk, Signals, and Recommendation.

### Acceptance Criteria
- [ ] T001.1 passes (valid package structure)
- [ ] T001.2 passes (empty input handling)
- [ ] INV001 enforced (risk_score bounds)
- [ ] INV002 enforced (signals not None)
- [ ] mypy passes with no errors
- [ ] 100% coverage on new code

### Estimated Effort
- Optimistic: 2 hours
- Likely: 4 hours
- Pessimistic: 8 hours
- **Planned**: 4 hours × 2.5 = 10 hours

### Dependencies
- None (first task)

### Pre-Conditions
- Test stubs T001.1-T001.5 exist (GATE 3)
- Types defined in architecture (GATE 1)

### Post-Conditions
- Tests T001.1-T001.5 pass (not skipped)
- src/phantom_guard/core/types.py exists
- Code has IMPLEMENTS: S001 comments

Step 3: Create Week Plans

Group tasks into weeks:

# docs/planning/ROADMAP.md

## Week 1: Core Types & Detection Engine

### Goals
- Implement S001-S005 (Core detection)
- All T001.* tests passing
- 90% coverage on core module

### Tasks

| Task | SPEC | Hours | Status |
|:-----|:-----|:------|:-------|
| W1.1 | S001 | 10 | PENDING |
| W1.2 | S002 | 8 | PENDING |
| W1.3 | S003 | 6 | PENDING |
| W1.4 | S004 | 8 | PENDING |
| W1.5 | S005 | 8 | PENDING |
| **Buffer** | - | 10 | - |
| **Total** | - | 50 | - |

### Exit Criteria
- [ ] All W1.* tasks complete
- [ ] T001-T005 tests passing
- [ ] Coverage ≥90% on core/
- [ ] Hostile review passed

---

## Week 2: Registry Clients

### Goals
- Implement S030-S055 (All registry clients)
- All T030-T055 tests passing
- Integration tests with live APIs

### Tasks

| Task | SPEC | Hours | Status |
|:-----|:-----|:------|:-------|
| W2.1 | S030-S035 | 12 | PENDING |
| W2.2 | S040-S045 | 12 | PENDING |
| W2.3 | S050-S055 | 12 | PENDING |
| W2.4 | Cache integration | 6 | PENDING |
| **Buffer** | - | 8 | - |
| **Total** | - | 50 | - |

### Exit Criteria
- [ ] All W2.* tasks complete
- [ ] T030-T055 tests passing
- [ ] Live API tests work
- [ ] Hostile review passed

Step 4: Create Dependency Graph

## DEPENDENCY GRAPH

W1.1 (Core Types) │ ├── W1.2 (Risk Scoring) ──┐ │ │ ├── W1.3 (Signal Detection)──┤ │ │ └── W1.4 (Pattern Matching)──┘ │ ▼ W1.5 (Detector Integration) │ ┌──────────────────┼──────────────────┐ │ │ │ ▼ ▼ ▼ W2.1 (PyPI) W2.2 (npm) W2.3 (crates) │ │ │ └──────────────────┼──────────────────┘ │ ▼ W2.4 (Cache Integration) │ ▼ W3.1 (CLI Interface)


### Critical Path
W1.1 → W1.5 → W2.1 → W2.4 → W3.1 → W4.1 (Release)

Step 5: Risk Assessment

## RISK ASSESSMENT

| Task | Risk Level | Risk Factor | Mitigation |
|:-----|:-----------|:------------|:-----------|
| W1.1 | LOW | Well-defined types | N/A |
| W1.2 | MEDIUM | Algorithm complexity | Property tests |
| W2.1 | HIGH | External API | Mocking, retries |
| W2.2 | HIGH | External API | Mocking, retries |
| W3.1 | LOW | Standard CLI patterns | typer framework |

### Contingency Plans

**If PyPI API changes:**
1. Switch to cached-only mode
2. Document regression
3. Implement new parser

**If rate limiting hit:**
1. Implement backoff
2. Add queue mechanism
3. Consider API key

ROADMAP DOCUMENT TEMPLATE

# Phantom Guard — Development Roadmap

> **Version**: 0.1.0
> **Created**: YYYY-MM-DD
> **Last Updated**: YYYY-MM-DD
> **Status**: ACTIVE

---

## Overview

### MVP Target
- Date: YYYY-MM-DD
- Scope: Core detection + CLI + 3 registries

### Total Effort
- Planned: X weeks
- Buffer: Y% contingency

---

## Phase 1: Core Engine (Weeks 1-2)

[Detailed week plans with tasks]

## Phase 2: Integrations (Weeks 3-4)

[Detailed week plans with tasks]

## Phase 3: CLI & Hooks (Weeks 5-6)

[Detailed week plans with tasks]

## Phase 4: Polish & Release (Weeks 7-8)

[Release preparation tasks]

---

## Task Registry

| Task ID | SPEC | Description | Hours | Status | Week |
|:--------|:-----|:------------|:------|:-------|:-----|
| W1.1 | S001 | Core types | 10 | PENDING | 1 |
| W1.2 | S002 | Risk scoring | 8 | PENDING | 1 |
| ... | ... | ... | ... | ... | ... |

---

## Progress Tracking

### Week 1
- [ ] W1.1 Complete
- [ ] W1.2 Complete
- [ ] Week 1 hostile review

### Week 2
...

---

## Trace Matrix

| Task | SPEC_IDs | INV_IDs | TEST_IDs |
|:-----|:---------|:--------|:---------|
| W1.1 | S001 | INV001, INV002 | T001.1-T001.5 |
| ... | ... | ... | ... |

GATE 4 EXIT CHECKLIST

Before Gate 4 is complete:

  • docs/planning/ROADMAP.md exists
  • Every task has SPEC trace
  • Every task has TEST trace
  • Every task < 8 hours
  • 20% buffer per week
  • Dependency graph defined
  • Risk assessment complete
  • HOSTILE_PLANNER review passed

If any checkbox fails: DO NOT PROCEED TO IMPLEMENTATION.


HOSTILE_PLANNER REVIEW

After completing roadmap:

/hostile-review planning

The reviewer checks:

  • Are estimates realistic?
  • Are dependencies correct?
  • Are traces complete?
  • Are risks identified?
  • Is critical path clear?

RECORDING GATE COMPLETION

# .fortress/gates/GATE_4_PLANNING.md

## Gate 4: Planning — COMPLETE

**Date**: YYYY-MM-DD
**Approver**: HOSTILE_PLANNER
**Output**: docs/planning/ROADMAP.md

### Summary
- X tasks defined
- Y weeks planned
- Z hours total (with buffer)

### Schedule
| Phase | Weeks | Hours |
|:------|:------|:------|
| Core | 1-2 | X |
| Integrations | 3-4 | Y |
| CLI | 5-6 | Z |
| Release | 7-8 | W |

### Next Step
Begin implementation with /implement W1.1

IMPLEMENTATION WORKFLOW

After Gate 4, use /implement for each task:

/implement W1.1

This triggers:

  1. Load task definition
  2. Verify pre-conditions
  3. TDD implementation cycle
  4. Verify post-conditions
  5. Mark task complete

PROTOCOL VIOLATIONS

Violation Response
Task without SPEC trace Add trace
Task > 8 hours Split task
No buffer in week Add 20% buffer
Skipped HOSTILE review Run review
Starting implementation without Gate 4 BLOCKED

Gate 4 is about PLANNING what to build. Gate 5 is about VALIDATING what was built.